| Basildon site - installation | ||
| Home | ||
The area chosen is adjacent to the front wall of the building just next to the
goods inwards doorway.
Generator and fuel tank in position with the inner wall cut our behind, ready for the air outlet attenuator.
Exhaust pipe disappearing out through the roof
|
There
was no possibility of siting the generator outside the building, so the decision was made
to position it within the
warehouse. The area chosen was adjacent to the goods inwards door under the mezzanine floor with the offices immediately above
it. The generator was to be housed in a specially designed block room. Once the generator and fuel tank had been delivered and positioned, the cabling between the main incomer room and the generator was fitted, and the exhaust pipe was installed. Once this was completed, the block room was built around the equipment, and this was followed by the installation of the ducting and air attenuators. Finally, the generator was connected up to the mains and tested to the customers satisfaction.
|
Inside the finished block room showing the generator and outlet ducting with a blue flexible connection between them
Electrical supply in the foreground, with the air inlet attenuator seen in the background
Fuel tank in foreground, air inlet attenuator, and electrical supply behind |